The conclusion of the supervisory authority states that Krasseti ignored the appeal of FGC UES about the need to comply with contractual obligations, including the agreed upon maximum power value. As a result, the installed technological protections against excess power were triggered. Also, in violation of regulatory rules, the company does not provide information about the volume of max. capacity in a timely manner. In addition, it turned out that a number of Krasseti’s own facilities are operating without permission from Rostechnadzor to be allowed into operation.
As for consumers, due to whom electricity consumption in the area has increased in recent months, then, according to the supervisory authority, the electrical equipment powered by Krasseti operates in violation of the current technical regulations. operation and installation of electrical installations. Apparently, we are talking about a mining farm located on the territory of the organization.
Earlier, a number of media reported about a conflict initiated by the Krasseti organization with FGC UES due to allegedly artificial restrictions in the transmission of electricity. The registrar also stated that supervisory authorities are not allowed into main power facilities for inspection. However, the current findings of Rostechnadzor indicate that the inspection was carried out without hindrance.
In response to the claims, the federal operator reported that it had an agreement with Krasseti for a capacity of 1.06 MW, while the actual consumption of Krasseti was more than 20 times higher. FGC UES assured that such unforeseen loads could lead to damage at the main substation, and, as a result, to a shutdown of the population, industry and railway infrastructure in the south of the Krasnoyarsk Territory. It also poses risks to the life and health of personnel. In this regard, the parameters of the technological protections of the 220 kV power center “Minusinskaya-Opornaya” were changed, and if the consumption volume specified in the technical connection act is significantly exceeded, the protections are automatically triggered. At the same time, the equipment of FGC UES is energized and is ready to provide electricity to Krasseti in accordance with the concluded agreement, the federal company said in the explanations. At the end of July, a number of telegram channels in the Krasnoyarsk Territory published photographs from a copter showing the placement of a large mining farm right on the territory of Krasseti energy facilities.
The findings of Rostechnadzor’s inspection were sent to the regional prosecutor’s office. Taking into account all the published circumstances, we can expect that the proceedings will be continued in relation to Krasseti itself.