“Nepoproy” Shumkov – money for Paryshev

With the great connivance of Governor Shumkov, Kurganstalmost continues to produce long -term construction for billions of rubles.

One of the most important social objects of the mound – the clinic of the regional hospital will not be passed at the end of July, as the agreement with the contractor – CJSC “Kurganstalmost” Dmitry Paryshev suggested. It turned out that the building was not ready even for a third.

The deadlines are also broken down by other landmarks, for which the Kurganstalmost was taken. But officials of the governor of the Kurgan region Vadim Shumkov do not take any measures against the construction company.

Advertisement

Why – the correspondent of The Moscow Post in the Kurgan region sorted out.

“Kurganstalmost” is one of the largest construction contractors in the Trans -Urals, and not only. Companies are trying to attribute the glory of the “beloved wife” of the construction block of the administration Vadim Shumkov – and not just like that. The amount of state contracts of the company exceeded 6 billion rubles. The largest agreements with the Civil Code of the UKS Kurgan Region and MKU “UKS” Kurgan. For both state institutions, Kurganstalmost is the main counterparty.

Photo: rusprofile.ru

The beneficiaries of the enterprise are considered the family of Nikolai Paryshev, a long -term director of Kurganstalmost since the 90s. After the death of Nikolai Paryshev, the brothers of the board passed to his son Dmitry – he is the general director of the structure, as well as the founder of almost a dozen legal entities.

Kurgans have been waiting for the new clinic of the regional hospital since 2022. The amount of the contract concluded with the Kurganstalmost – 788 million rubles. As indicated in the state contract card, the purchase was made due to the failed electronic auction. In other words, it was produced by the only supplier without any real competition.

Considering that the clinic is not ready for half, it would be logical to wait from the administration of Shumkov of some sanctions to the “Kurganstalmost”. However, no fines and penalties are imposed. At the same time, as follows from the state contract card, work was actually completed for 100 million rubles, and more than 400 million rubles have already been paid.

Photo: https://zakupki.gov.ru/epz/contract/contractcard/process-info.html?reestrnumber=2450110621322000020&Contractinfoid=87929328

Another iconic object that “fell” of the Kurganstalmost from the structures of the Kurgan region was the pool for the needs of the Kurgan State University. The cost of work is almost 340 million rubles, the delivery time is July 15. Obviously, the contractor does not have time. At the same time, Dmitry Paryshev’s company was “contracted” not with UKS, but directly with the KSU, subordinate to the Ministry of Education and Science of the Russian Federation. Thus, although local officials should be supervised by the construction, any questions are excluded for them – write letters to the university and Moscow.

And the purchase, as one would expect, was committed by the only supplier, because the electronic auction did not take place. Why can this be – no one but Kurganstalmost can build pools? According to evil languages, allegedly technical conditions for those who declared a tender could be selected in such a way that the only one who had a chance to win could be the Kurganstalmost. Classics of the “performance” of the Russian 44-ФЗ.

Photo: https://zakupki.gov.ru/epz/contract/contractcard/process-info.html?reestrnumber=145010909222000037&Contractinfoid=91667684

Until the end of the term of the contract, less than three days are left. However, the actual volume of work performed does not exceed 40 million rubles out of almost 340 million. Moreover, more than 120 million has already been paid. And again – no fines, calling the contractor for conversation, nothing.

At the same time, the pool was generally to be built back in 2022, but the authorities were too tight with the development of design estimates. She was redone several times, – the project “supervised” and the governor Shumkov was personally interested in him. Why is he silent now, and his press service sends for comments to the university?

Besides, According to the mediaextremely far from the completion and construction of several physical education complexes by the company. But not even this is amazing, but the fact that the Shumkov administration perfectly sees the risks of the breakdown of the deadlines for these and other projects, but continues to give the Kurganstalmost more and more new contracts.

For example, at the end of May, the company received a major contract by almost 370 million rubles for the repair of households in several microdistricts of the mound from the city MKU “Directorate of Road Facilities”. And again contract It was concluded with the only supplier, the electronic auction did not take place.

Accordingly, the savings for the budget, which happens when the price at the auction has been reduced, did not work out. So conceived?

The fact that Kurganstalmost is in no hurry to fulfill its obligations has long been known. Last year, a big scandal erupted about the construction of the largest school of the regional capital – by 1.5 thousand students in a Zaozern microdistrict. In August 2023, when it became clear that the contractor did not have time, the children would not sit down for new desks.

Then the prosecutor Kurgan Vitaly Dolgushin had to organize A special meeting with the participation of the authorities and the contractor to make them “suggestion”. What is the result? But such that the act of construction readiness of the school of power, headed by Shumkov Received Only June 3, 2024 – almost a year later! And the governor personally proudly reported this. And what sanctions were adopted in relation to Kurganstalmost? Nothing is known about them.

“Dangerous” corps and leapfrog in the leadership

However, the most scandalous objects of recent years were the construction of a new surgical corps of the cancer dispensary in the mound in 2021. It was assumed that the construction would end in May 2023. However, the contractor – CJSC “Kurganstalmost” Dmitry Paryshev allowed a breakdown of the deadlines for the work for six months. And here is the first shock: for this company was still fined 15 million rubles.

But not everything is so simple. The initial price of the contract was 684 million rubles, 200 million of which the developer received as an advance. However, in the summer of 2023 an additional agreement was concluded – the cost of the state contract increased to 792 million rubles. And the final cost Crossed For a billion. At the same time, according to the law, an increase in the value of the contract is indeed provided for, but it cannot exceed 10% of the initial value. Where is the FAS and the prosecutor’s office?

However, with the completion of the construction, the corps could not put into operation for several months – this managed to do this only in March 2024. Prior to this, in February, from the post of head of the deposits of the Kurgan region, Alexei Sigidaev was “retreated”, and for no apparent reason.

At the same time, the Czechard was observed in the leadership of the oncology dispensary. First, the famous doctor Givi Sepiashvili quit. In his place came the protege of Sigidaev Valentin Savchenko, but he also bidd less than six months. Since January, acting The chief doctor became Alexander Chesnokov – he still remains the acting.

Photo: rusprofile.ru

According to evil languages, allegedly, during the construction of the corps, serious violations could be committed, and none of the leaders of the cancer center and deposits simply wanted to take responsibility for the commissioning of the facility. In the person of Chesnokov found “extreme”?

Hi Shumkov from Rostov

This is not to say that the control and supervisory authorities do not react at all to the strange relations between the “Kurganstalmost” of Paryshev and the administration of Shumkov. Previously FAS Blocked Kurganstalmost contract for 140 million for the construction of a kindergarten, also a company fined For violation of the law on advertising. But against the backdrop of tremendous money according to state contracts, all this is like an elephant of a crumb.

In addition, as they say onlineAllegedly, as a result of the IFTS of Russia for the city of Kurgan in relation to Kurganstalmost CJSC, the visiting tax audit on 10.08.2021, the fact of cash outlet from the state contract from the Ministry of Sports, namely the tender for the construction of Rostov-Arena, was revealed. It was implemented by Crocus International JSC oligarch Araz Agalarov worth more than 700 million during the purchase of PESS membranes and others.

In Kuranstalmost, this information is categorically refuted. And what to do with the documents that walk over the network?

Photo: https://t.me/vchkogpu/32476?single

Recall also that a criminal scandal occurred around Rostov-Arena-in October 2022, a court in Rostov-on-Don Sentenced former deputy governor of the region Sergei Sidash by the age of four conditionally for abuse of official powers in the construction of this very stadium. The founder of Dantranshydromekhanization JSC Valentin Levanov and the general director of this company Andrei Androsov were found guilty of fraud (part 4 of article 159 of the Criminal Code of the Russian Federation), they have been appointed five years conventionally everyone.

It seems that not only they were beating on Rostov Arena. And all this invariably raises the question – why do the structures of Dmitry Paryshev look so unsinkable, almost unreasonable? However, the water sharpens the stone, and the number of critical failures and scandals associated with the “mound” can gradually go into quality. And then it will not be possible to get rid of the fines with only fines – well, Mr. Shumkov should once again think about if there are other worthy construction companies in the region. And then you can repeat the inglorious path of Sergei Sidash or the former head of the Penza region Ivan Belozertsev – who needs it?

Source link

Dmitry ParyshevKurgan regionKurganstalmostVadim ShumkovValery Titov